Two construction field leads review a slab bay plan outside a barricade while the concrete formwork and shores remain in place.

Make the removal decision for one exact bay

We would not send the strip crew into a floor wide instruction. The decision needs to cover the exact bay, the forms or shores being removed, and the loads that will follow.

For the cast in place work covered here, OSHA 29 CFR 1926.703(e) requires the employer to determine that the concrete can support its weight and the loads placed on it before forms and shores are removed, subject to the stated exceptions. The rule allows that determination to follow the conditions in the plans and specifications or the results of an appropriate ASTM compressive strength test. Reshore removal has its own strength and loading requirement.

If the next trade changed its staging plan, put that change in front of the person responsible for the determination before the strip crew receives instructions.

Three questions for the pretask meeting

  1. Which area are we talking about? Mark the level and bay on the current drawing. State what the crew will remove and what must remain.

  2. What evidence applies here? Ask the responsible person to point to the plan condition and show how it was met, or identify the relevant test result. Confirm that the evidence covers this placement and this removal area.

  3. What load comes next? Put planned material staging and equipment access beside the removal decision. If the location, sequence, or load changed, hold the affected work for review under the approved project process.

Use the free Construction Risk Radar to record the bay, the limit of the decision, where the evidence lives, and who reviews a change.

Leave the foreman a decision that can be repeated

Before assigning the next strip crew, read the decision back with the foreman who will use it. If the evidence or its limits are unclear, leave that bay on hold and name the person who will resolve it.

Source note: OSHA 29 CFR 1926.703(e)(1), (2), and (3), reviewed November 11, 2026. Apply the full standard, the project plans and specifications, and the employer's approved removal process.