Measure the temporary heat setup before startup
Cold weather can turn a heater setup into a rushed decision. We would not open a fuel valve or energize a unit until someone checks the exact heater, the listed instructions, nearby materials, the air supply, and the path to the extinguisher.

THE DIG DAILY DOSE
Before Temporary Heat Starts, Check the Clearance
OSHA 29 CFR 1926.154 addresses fresh air, clearances from combustible material, stable mounting, and controls for fuel fired heaters. A unit that worked in yesterday's open area may not be acceptable after crews hang tarps, stack material, or close the building in.
Three checks before temporary heat starts
Match the clearance to the heater. Read the nameplate and listed instructions. Measure to tarps, lumber, packaging, stored finishes, and every other combustible. A listed unit may use its approved clearances.
Check the base, ventilation, and fuel setup. Make sure the heater is level, protected from upset, and allowed on the supporting surface. If natural air is not enough, provide mechanical ventilation before startup. Check fuel lines, tanks, and flame failure controls against the unit's requirements.
Keep fire protection ready. Remove unnecessary combustibles, secure coverings against wind movement, and keep the path to a suitable extinguisher clear. OSHA 29 CFR 1926.150 requires accessible, conspicuously located, operating firefighting equipment as hazards develop.
Record the heater, measured clearances, ventilation, fuel controls, and extinguisher in the free Construction Risk Radar.
Numbers to verify at the workface
OSHA Table F-4 lists 12 inches at the sides and rear of a circulating room heater and 18 inches at the chimney connector, unless the listed approval permits another installation.
For a radiant room heater, the table lists 36 inches at the sides and rear and 18 inches at the chimney connector, subject to the same listed equipment provision.
Keep temporary heaters at least 10 feet from combustible tarps, canvas, and similar coverings. Secure those coverings against ignition or heater upset from wind.
Have the person responsible for temporary heat point to each condition. If the setup changes after approval, stop and repeat the check before restart.
Source note: OSHA 29 CFR 1926.154, including Table F-4, and 29 CFR 1926.150, reviewed November 14, 2026. Apply the full rules and the heater's listed instructions.